Entry 7: Filling Proba-2 up with xenon

532 views 0 likes
ESA / Enabling & Support / Space Engineering & Technology / Proba Missions

Tuesday, 8 September - Today's activities mainly focus on the finalisation of one of Proba-2's plasma measurement instruments – the Dual Segmented Langmuir Probe - and its cold gas propulsion system. The DSLP probes are being mounted on one of the deployable solar panels and equipped with specific sensor stimuli. A final experiment test is carried out to gather a set of reference data prior to launch. Test results are send to the principal investigator from the Czech Republic for further analysis and post processing.

The technology demonstrator which requires the team's specific attention today is the xenon cold gas propulsion system (developed by UK-based Surrey Satellite Technology, SSTL). First of all a leak test of the complete system is performed, prior to beginning to fill the tank with the xenon propellant. This is a tedious task requiring close monitoring of pressure and temperature.

In meantime interface discussions with the Russian launcher team continue in preparation for the combined launch operation activities for the spacecraft mating sequence, the umbilical check-out and the battery charging.

Considering the amount of co-ordination meetings the Proba-2 team have already had, for this 'small satellite' project, they are already getting a flavour of what to expect in the weeks to follow. That is when the team will be perform joint operations with the SMOS team, Eurockot, Krunichev and the local military and space forces...

Concluding a busy day, Proba-2 is powered up in order to obtain telemetry readings of the propulsion system, confirming a tank pressure of 30bar in line with earlier EGSE (electrical ground support equipment) measurements.

Related Links

Proba-2, final checks
Enabling & Support

Entry 1: Belgium says goodbye to Proba-2

469 views 0 likes
Read
Loading of Proba-2 container in cargo plane at Brussels airport
Enabling & Support

Entry 2: Proba-2's journey to Plesetsk

490 views 0 likes
Read
Transport of Proba-2 container to the MIK
Enabling & Support

Entry 3: Unpacking after the trip

351 views 1 likes
Read
Opening of the Proba-2 satellite container in the cleanroom
Enabling & Support

Entry 4: Proba-2 unloaded and ready for inspection

422 views 0 likes
Read
Hoisting of satellite from its container and assembly of integration dolly
Enabling & Support

Entry 5: Proba-2 powered up

446 views 0 likes
Read
Inspection of Proba-2 internal compartments
Enabling & Support

Entry 6: End-to-end testing

611 views 0 likes
Read
Filling of the propulsion tank with xeon
Enabling & Support

Entry 7: Filling Proba-2 up with xenon

532 views 0 likes
Read
Mounting of the first deployable solar panel
Enabling & Support

Entry 8: Proba-2 gains a solar panel

542 views 0 likes
Read
Mounting of solar panel
Enabling & Support

Entry 9: Proba-2 gains its second ‘wing’

364 views 0 likes
Read
Proba-2 with solar panels mounted
Enabling & Support

Entry 10: Completing Proba-2

375 views 0 likes
Read
Proba-2 final full functional test
Enabling & Support

Entry 11: Putting Proba-2 to the test

454 views 0 likes
Read
Proba-2 launch team group picture at the museum
Enabling & Support

Entry 12: Checking launch tower links

370 views 0 likes
Read
Proba-2 back in its storage container in the cleanroom
Enabling & Support

Entry 13: Letting SMOS take its turn

420 views 0 likes
Read
Proba-2 team arrival at Plesetsk Cosmodrome
Enabling & Support

Entry 14: Second phase of Proba-2 launch campaign begins

400 views 0 likes
Read
ESP mounting on the final panel
Enabling & Support

Entry 15: Last bolts tightened on Proba-2

399 views 0 likes
Read
Proba-2
Enabling & Support

Entry 16: A short journey off the ground – Proba-2 mated to…

403 views 0 likes
Read
Proba-2 in its final launch position, on top of Breeze
Enabling & Support

Entry 17: Proba-2 mated onto Breeze upper stage

530 views 0 likes
Read
Removal of Proba-2 protective covers
Enabling & Support

Entry 18: Encapsulated, Proba-2 vanishes from view forever

432 views 0 likes
Read
Encapsulation
Enabling & Support

Entry 19: Proba-2 in place and powered up

379 views 0 likes
Read
SMOS, Proba-2 and Khrunichev teams
Enabling & Support

Entry 20: Rail ride to the launch pad

520 views 1 likes
Read
Joined dress rehearsal of Proba-2 and SMOS in MCC
Enabling & Support

Entry 21: Far-flung dress rehearsal for launch

900 views 0 likes
Read